Public Transport Operations Control Centre
East Perth, WA
East Perth, WA Public Transport Operations Control Centre
The Public Transport Operations Control Centre (PTOCC) is ADCO’s second project for the Western Australian government’s METRONET infrastructure development.
This $72 million project, part of the METRONET initiative, involved building a 6-storey facility to support the High-Capacity Signalling (HCS) project. The construction used 700 tonnes of precast panels, 5,500m³ of concrete, and 1,000 tonnes of reinforcement. Design optimisations saved 500m³ of concrete, 2 weeks, and 200-tonnes of reinforcement. The project also included a High-Voltage room, bike store, car park, and public artwork titled ‘Kulbardi Season’.
The fit out phase involved creating a Central Monitoring Room with 20 operator desks, a large DvLED video wall, a raised access floor, as well as a new interim Network Control Centre and an internal curtain wall with acoustically rated glazing. Extensive collaboration with stakeholders and meticulous planning were required to meet the PTA’s 24/7 operational requirements. ADCO received commendation from the PTA for delivering a high-quality and robust facility with premium finishes within the agreed timeframe.
This project highlights ADCO’s ability to deliver high-quality infrastructure projects on time and within budget.
-
type
ECI to Design & Construct
-
value
$72 million
-
duration
24 months (base build) / 6 months (fit out)